Atlantic LNG Jetty (Trinidad)

Atlantic LNG Jetty

  • Client Name: Pres-T-Con Ltd
  • Client Sector: Oil & Gas
  • Project Value: US$12.80 Million
  • Services Provided: Contract Advice / Dispute Resolution
  • Project Size: circa 35 meter long service jetty
  • Engineer: Lee Young & Partners
  • Contractor: Pres-T-Con Ltd

A jetty for Atlantic LNG to serve as a roadway, a pipe rack and utility rack. It was designed to be 36 meters long by 16 meters wide and is located in Point Fortin, Trinidad and Tobago.

Key Issues

This was the second similar facility constructed by Pres-T-Con Ltd and a potential dispute arose over the interpretation of a change in the IBC code for construction.Bould Consulting Limited through alliance partner CCAS provided construction contract advice and claim settlement strategy to contractors Pres-T-Con Ltd on the construction of the jetty for a LNG gas facility on Port Lisas Trinidad

OUR ROLE

Client Benefit

Bould Consulting Limited provided significant analysis advice and opinion on delays due to contract signing coupled with design changes and testing laboratory verifications and consequent loss and expense claims, which was successfully negotiated to a most satisfactory settlement to the Client.